Demolition of existing 1970ʼs two storey ROSLA unit including asbestos removal. Construction of a new single storey teaching block. The domestic science room included a full fit out of food technology equipment. The cafeteria including full catering equipment fit-out was designed for use by the general public as part of the schools integration with the local community. Construction cost engineered down from an original bid value of approaching £700,000.00 to £550,000.00 with reductions approaching £150,000.00 were achieved with reduced specifications, economies, value engineering and price reductions.